hero-background-about hero-background-about

Audit and assessment of environmental and social responsibility

Project operations and outcomes are assessed and brought in line with international standards
  • Environmental and Social audit in accordance with EBRD/IFC/EIB Environmental and Social Policies and Guidelines

  • Phase I, II and III of Environmental Site Assessment of Greenfield and Brownfield sites in accordance with ASTM E 1527-05 and ASTM E 1903

  • Environmental Impact Assessment according to the Law of Ukraine 2059-VIII dated May 23, 2017, and EU Directive 2011/92/EU

  • Asbestos survey, development of asbestos remediation plan

  • Assessment and certification of construction objects according to BREEAM International New Construction

  • Environmental and occupational health safety supervision in construction according to FIDIC and NEBOSH standards

  • Development and implementation of RECP measures (resource-efficient and cleaner production)

Our projects

project

NEPTUNE grain terminal

Pivdennyi Sea Port, Odessa region
Customer:
MV Cargo
Role:
Project management for technical part of the project.
Result:
More than 600 contractors and suppliers, as well as more than 500 workers were involved at the peak of construction.
project

FORUM LVIV

Lviv city
Customer:
MULTI Development Ukraine LLC
Role:
Assessment and certification of FORUM LVIV shopping and entertainment center according to BREEAM International environmental standard.
Result:
FORUM LVIV became the first shopping and entertainment center in Ukraine certified according to the BREEAM International standard.
project

Rive Gauche shopping center and Retail Park Petrivka

Kyiv city
Customer:
IMMOCHAN
Role:
Coordinating tenant adaptation in 2 shopping centers.
Result:
Works performed by tenants were checked and ensured to comply with the requirements of the international developer’s project.
project

Fuel business of SCM Holding

Сustomer:
SCM (35 objects in Donetsk, Luhansk and Zaporizhzhia regions).
Role:
Construction audit and revealing potential corruption points. Optimising construction budget.
Result:
Saving 16% of construction budget and 17% in schedule.
project

Barabashovo market

Kharkiv city
Customer:
CONCERN AVEC AND CO
Role:
2017: technical audit of the shopping center. GBA: over 75 hectares. 2018-2019: survey of the capital costs of the shopping center with the formation of reports for financing organizations (banks).
Result:
2017: a large-scale audit was performed. 2018-2019: quarterly surveying of capital expenditures was carried out in accordance with the developed budget to eliminate the identified risks.
project

Multiplex сinema

Kyiv city
Customer:
Multiplex
Role:
Management of contract works during construction of cinema in Sky Mall shopping center.
Result:
Сonstruction of 10 cinema halls with full operational capability.
project

TIS

Odesa region
Customer:
TIS
Role:
Coordinating construction projects of railway defroster and “blue re-bar” warehouse.
Result:
2015-2017: the objects were put into operation according to the schedules and within the budget.
KEY Group in figures
0 years
in construction project management
$ 0
total cost of objects
0 m 2
загальна площа об’єктів
0
total number of workers during our assignments
Our clients
client
client
client
client
client
client
client
client